DAKOTA COUNTY TRANSPORTATION DEPARTMENT

DAKOTA COUNTY, MINNESOTA

 

 

Notice is hereby given that electronic bids will be accepted by Dakota County for the aforementioned project through Dakota County's online electronic bid system (eGram), until 11:00 AM on Monday, December 9, 2019, at which time they will be publicly opened and read at the Empire Transportation Facility located at 2800 160th Street West, Rosemount, MN.

 


The 2019 Dakota County Overlays & Miscellaneous Projects contract (Contract No. 32163) includes the following projects:

CP 08-28: Mill & overlay, pedestrian improvements, and utility repairs on CSAH 8 (Wentworth Avenue) from Crawford Drive to Christensen Avenue in West St. Paul
CP 08-29: Mill & overlay and pedestrian curb ramp improvements on CR/CSAH 8 (Wachtler Avenue/Wentworth Avenue) from TH 13 to CSAH 63 in Mendota Heights
CP 14-31: Sidewalk removal & replacement on CSAH 14 from Marie Avenue to TH 156 in South St. Paul
CP 14-32: Mill & overlay on CSAH 14 from Marie Avenue to TH 156 in South St. Paul
CP 32-102: Mill & overlay and right turn lane construction on CSAH 32 (Cliff Road) from TH 3 to CSAH 71 in Eagan and Inver Grove Heights
CP 42-155: Pedestrian curb ramp improvements at CSAH 42 & Garrett Avenue in Apple Valley
CP 43-51: Pedestrian crossing improvements on CSAH 43 (Lexington Avenue) south of Northview Park Road in Eagan
CP 63-28: Mill & overlay, shoulder widening, and utility repairs on CSAH 63 (Delaware Avenue) from south of TH 62 to TH 149 in Mendota Heights and West St. Paul
CP 85-21: Mill & overlay on CSAH 85 (Goodwin Avenue) from TH 50 in Hampton Township to CSAH 62 in Vermillion Township
CP 98-009: Mill & overlay the west & east parking lots at the Northern Service Center in West St. Paul
CP 98-010: Trail reclamation & paving on the Big Rivers Regional Trail (along TH 13) in Mendota Heights and Lilydale and Mississippi River Regional Trail (east of Hardman Avenue) in South St. Paul, mill & overlay of the Camp Sacajawea entrance road (adjacent to CSAH 38) and overlay of trails in Camp Sacajawea in Apple Valley
CP 98-014: Concrete walk construction (for bus shelters) at various locations on the County system
CP 98-015: Bituminous paving on Dakota Way from 2nd Street to 4th Street within the Dakota County Fairgrounds
 

 
The major items of work include approximately:



251,000 SQ. YD. OF MILL BITUMINOUS SURFACE
40,000 TONS of 2360 WEARING COURSE MIXTURE
1 SIGNAL REVISION
19,500 SQ. FT. of CONCRETE WALK
1,400 LIN. FT. of CONCRETE CURB & GUTTER
176,000 LIN. FT. of PAVEMENT MARKINGS- MULTI COMP
1,700 SQ. FT. of PAVEMENT MESSAGE-MULTI COM
270 LIN. FT. of PAVEMENT MARKINGS- PREFORM TAPE
300 SQ. FT. of PAVEMENT MESSAGE/CROSSWALK-PREFORM TAPE


DIGITAL COPIES OF THE BIDDING DOCUMENTS ARE AVAILABLE AT:

http://www.co.dakota.mn.us/Government/DoingBusiness/BidProposalsInformation/Pages/transportation.aspx

 

These documents may be downloaded at https://egram.co.dakota.mn.us (Projects in Bidding). Bidders are responsible for all present and future downloads, including addendums and their attachments.

 

Paper documents are also available for viewing only weekdays between 8:00 AM and 4:30 PM at the County Engineer's Office, (952-891-7100) 14955 Galaxie Avenue, Apple Valley, MN 55124.

 

***ONLY REGISTERED PLANHOLDERS WILL BE ALLOWED TO BID ON PROJECTS***

There is no cost to register or download the Project Plans and Proposal documents. To become a registered plan holder, you must create an account at:  https://connex.mn.uccs.com

 

Bids must be accompanied by a certified check or corporate surety bond, made in favor of Dakota County in an amount of at least 5% of the amount bid. The right is reserved to accept or reject any or all bids and to waive any informalities therein.

 

It is anticipated that a contract to perform the work will be awarded by resolution of the Dakota County Board of Commissioners at the County Board meeting scheduled for Tuesday, December 17, 2019.