42-158 - 2020 Overlays & Misc. Projects | Bituminous Roadways, Inc. | OMG Midwest Inc. dba Minnesota Paving & Materials | McNamara Contracting, Inc. |
Item No. | Item | Units | Quantity | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
2104.503 | SAWING BIT PAVEMENT (FULL DEPTH) | L F | 33 | $3.90 | $128.70 | $2.27 | $74.91 | $3.00 | $99.00 |
2104.503 | REMOVE CURB & GUTTER | L F | 192 | $6.70 | $1,286.40 | $12.96 | $2,488.32 | $12.00 | $2,304.00 |
2104.518 | REMOVE CONCRETE DRIVEWAY PAVEMENT | S F | 1,047 | $1.40 | $1,465.80 | $3.93 | $4,114.71 | $3.00 | $3,141.00 |
2104.518 | REMOVE BITUMINOUS PAVEMENT | S F | 458 | $0.50 | $229.00 | $1.69 | $774.02 | $1.00 | $458.00 |
2521.518 | 3" BITUMINOUS WALK | S F | 368 | $2.00 | $736.00 | $4.37 | $1,608.16 | $8.00 | $2,944.00 |
2531.503 | CONCRETE CURB & GUTTER DESIGN B618 | L F | 87 | $34.00 | $2,958.00 | $43.35 | $3,771.45 | $75.00 | $6,525.00 |
2563.601 | TRAFFIC CONTROL | LS | 1 | $8,278.00 | $8,278.00 | $4,513.11 | $4,513.11 | $9,000.00 | $9,000.00 |
2574.507 | COMMON TOPSOIL BORROW | C Y | 200 | $48.50 | $9,700.00 | $50.15 | $10,030.00 | $51.00 | $10,200.00 |
2575.604 | SEEDING | S Y | 142 | $12.50 | $1,775.00 | $7.02 | $996.84 | $13.00 | $1,846.00 |
| Totals for project 42-158 | | $26,556.90 | | $28,371.52 | | $36,517.00 |
|
Contract Total: | $26,556.90 | $28,371.52 | $36,517.00 |