Bid Abstract

28-61 - 2020 Overlays & Misc. ProjectsBituminous Roadways, Inc. OMG Midwest Inc. dba Minnesota Paving & Materials McNamara Contracting, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2104.502REMOVE GATE VALVE & BOXEACH3$1,643.00$4,929.00$2,507.29$7,521.87$457.78$1,373.34
2104.502REMOVE CASTING & RINGS (STORM)EACH63$94.50$5,953.50$163.84$10,321.92$220.66$13,901.58
2104.502REMOVE CASTING & RINGS (SANITARY)EACH7$94.50$661.50$163.84$1,146.88$165.26$1,156.82
2104.502REMOVE DRAINAGE STRUCTUREEACH2$1,084.00$2,168.00$2,131.89$4,263.78$915.56$1,831.12
2104.503REMOVE CURB & GUTTERL F770$6.70$5,159.00$11.10$8,547.00$21.95$16,901.50
2104.503REMOVE CURB & GUTTERL F1,730$6.70$11,591.00$11.08$19,168.40$20.39$35,274.70
2104.503SAWING BIT PAVEMENT (FULL DEPTH)L F560$3.90$2,184.00$2.27$1,271.20$3.12$1,747.20
2104.518REMOVE CONCRETE WALKS F2,880$1.20$3,456.00$3.69$10,627.20$4.16$11,980.80
2104.518REMOVE BITUMINOUS WALKS F1,315$0.65$854.75$1.35$1,775.25$2.08$2,735.20
2104.518REMOVE BITUMINOUS PAVEMENTS F3,267$0.50$1,633.50$1.35$4,410.45$2.60$8,494.20
2104.518REMOVE CONCRETE DRIVEWAY PAVEMENTS F680$1.40$952.00$3.06$2,080.80$5.20$3,536.00
2104.602REMOVE GATE VALVE TOP SECTIONEACH31$129.00$3,999.00$122.88$3,809.28$241.53$7,487.43
2104.618REMOVE AND REPLACE BITUMINOUS PAVEMENTS F371$7.00$2,597.00$7.86$2,916.06$8.60$3,190.60
2211.509AGGREGATE BASE CLASS 5TON115$23.50$2,702.50$38.90$4,473.50$25.31$2,910.65
2232.504MILL BITUMINOUS SURFACE (2.0")S Y65,674$0.85$55,822.90$1.25$82,092.50$0.95$62,390.30
2357.506BITUMINOUS MATERIAL FOR TACK COAT (P)GAL3,284$3.00$9,852.00$1.60$5,254.40$1.55$5,090.20
2360.509TYPE SP 12.5 WEARING COURSE MIX (3;B)TON7,897$37.50$296,137.50$56.08$442,863.76$54.30$428,807.10
2503.602CONSTRUCT BULKHEADEACH1$942.00$942.00$2,131.89$2,131.89$957.17$957.17
2503.602RECONSTRUCT SANITARY MANHOLEEACH6$3,766.00$22,596.00$4,232.94$25,397.64$6,762.63$40,575.78
2503.602EXTERNAL MANHOLE CHIMNEY SEALEACH13$362.00$4,706.00$150.44$1,955.72$183.59$2,386.67
2504.602GATE VALVE TOP SECTIONEACH31$294.00$9,114.00$332.23$10,299.13$430.14$13,334.34
2504.602GATE VALVE BOXEACH3$2,168.00$6,504.00$4,520.82$13,562.46$2,132.83$6,398.49
2506.502CONST DRAINAGE STRUCTURE DES 48-4020EACH1$5,524.00$5,524.00$6,961.29$6,961.29$7,074.75$7,074.75
2506.602CASTING & RINGS (R-3067-V)EACH25$1,166.00$29,150.00$774.71$19,367.75$891.57$22,289.25
2506.602CASTING & RINGS (R-1642) (SANITARY)EACH7$967.00$6,769.00$784.78$5,493.46$1,028.84$7,201.88
2506.602RECONSTRUCT STORM SEWER MANHOLEEACH2$3,253.00$6,506.00$4,104.30$8,208.60$7,594.95$15,189.90
2506.602REMOVE & REPLACE INVERTS/DOGHOUSESEACH4$542.00$2,168.00$647.88$2,591.52$2,469.97$9,879.88
2506.602CASTING & RINGS (R-3250-DVSP)EACH26$1,319.00$34,294.00$915.12$23,793.12$1,046.95$27,220.70
2506.602CONNECT INTO EXISTING STORM SEWEREACH2$1,255.00$2,510.00$1,816.78$3,633.56$998.79$1,997.58
2506.602INTERNAL ADJUSTING RING SEALANT (SANITARY)EACH13$690.00$8,970.00$377.10$4,902.30$566.50$7,364.50
2506.602INTERNAL ADJUSTING RING SEALANT (STORM)EACH73$690.00$50,370.00$591.72$43,195.56$566.50$41,354.50
2506.602CASTING & RINGS (R-1642)EACH12$967.00$11,604.00$784.78$9,417.36$1,028.67$12,344.04
2521.5183" BITUMINOUS WALKS F171$2.00$342.00$4.51$771.21$7.25$1,239.75
2521.5183" CONCRETE WALKS F625$6.70$4,187.50$6.80$4,250.00$9.31$5,818.75
2521.5186" CONCRETE WALKS F5,181$15.00$77,715.00$12.86$66,627.66$15.50$80,305.50
2531.503CONCRETE CURB & GUTTER DESIGN B618L F1,730$105.00$181,650.00$40.02$69,234.60$31.26$54,079.80
2531.503CONCRETE CURB & GUTTER DESIGN B618L F1,042$34.00$35,428.00$40.17$41,857.14$35.70$37,199.40
2531.503CONCRETE CURB DESIGN V6L F168$57.00$9,576.00$61.85$10,390.80$46.94$7,885.92
2531.5046" CONCRETE DRIVEWAY PAVEMENTS Y76$88.00$6,688.00$91.22$6,932.72$103.68$7,879.68
2531.618TRUNCATED DOMESS F702$73.50$51,597.00$65.19$45,763.38$51.50$36,153.00
2563.601TRAFFIC CONTROLLS1$11,430.00$11,430.00$40,239.86$40,239.86$66,680.46$66,680.46
2563.601TRAFFIC CONTROLLS1$10,181.00$10,181.00$4,513.11$4,513.11$36,753.01$36,753.01
2565.616REVISE SIGNAL SYSTEM GSYS1$29,711.00$29,711.00$24,345.00$24,345.00$25,600.00$25,600.00
2565.616REVISE SIGNAL SYSTEM HSYS1$26,700.00$26,700.00$24,496.00$24,496.00$25,800.00$25,800.00
2573.502STORM DRAIN INLET PROTECTIONEACH66$190.00$12,540.00$150.44$9,929.04$150.00$9,900.00
2574.507BOULEVARD TOPSOIL BORROWC Y82$48.50$3,977.00$50.15$4,112.30$50.47$4,138.54
2575.504SODDING TYPE SALT TOLERANTS Y467$29.00$13,543.00$30.09$14,052.03$9.79$4,571.93
2575.602SITE RESTORATIONEACH33$615.00$20,295.00$877.55$28,959.15$283.25$9,347.25
2582.50324" SOLID LINE MULTI COMPL F495$7.80$3,861.00$7.02$3,474.90$7.21$3,568.95
2582.5034" DOTTED LINE PREF TAPE (WR)L F146$6.70$978.20$6.02$878.92$6.18$902.28
2582.5034" BROKEN LINE MULTI COMPL F1,950$0.25$487.50$0.23$448.50$0.24$468.00
2582.5034" SOLID LINE MULTI COMPL F39,500$0.25$9,875.00$0.23$9,085.00$0.24$9,480.00
2582.50312" SOLID LINE MULTI COMPL F154$3.90$600.60$3.51$540.54$3.61$555.94
2582.5034" BROKEN LINE PREF TAPE (WR)L F240$6.70$1,608.00$6.02$1,444.80$6.18$1,483.20
2582.50324" SOLID LINE PREF TAPE GR IN (WR)L F276$27.00$7,452.00$24.07$6,643.32$24.72$6,822.72
2582.50312" SOLID LINE PREF TAPE GR IN (WR)L F1,265$13.50$17,077.50$12.03$15,217.95$12.36$15,635.40
2582.518CROSSWALK MULTI COMPS F528$6.70$3,537.60$6.02$3,178.56$6.18$3,263.04
2582.518PAVT MSSG PREF TAPE (WR)S F420$24.00$10,080.00$21.73$9,126.60$22.32$9,374.40
2582.518PAVT MSSG MULTI COMPS F359$8.90$3,195.10$8.02$2,879.18$8.24$2,958.16
 Totals for project 28-61 $1,166,693.15 $1,242,847.88 $1,292,243.25
 
Contract Total:$1,166,693.15$1,242,847.88$1,292,243.25