85-21 - 2019 Overlay & Misc. Projects (2020 Season) | McNamara Contracting, Inc. | Bituminous Roadways, Inc. | Hardrives, Inc. | Valley Paving Inc |
Item No. | Item | Units | Quantity | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
2221.509 | SHOULDER BASE AGGREGATE CLASS 2 MOD | TON | 309 | $60.00 | $18,540.00 | $44.00 | $13,596.00 | $20.56 | $6,353.04 | $41.67 | $12,876.03 |
2232.504 | MILL BITUMINOUS SURFACE (1.0") | S Y | 70,003 | $0.70 | $49,002.10 | $0.65 | $45,501.95 | $1.44 | $100,804.32 | $0.79 | $55,302.37 |
2232.504 | MILL BITUMINOUS SURFACE (2.0") | S Y | 3,028 | $5.00 | $15,140.00 | $1.30 | $3,936.40 | $3.13 | $9,477.64 | $6.61 | $20,015.08 |
2357.506 | BITUMINOUS MATERIAL FOR TACK COAT (P) | GAL | 6,042 | $2.00 | $12,084.00 | $3.80 | $22,959.60 | $1.60 | $9,667.20 | $2.71 | $16,373.82 |
2360.509 | TYPE SP 9.5 WEARING COURSE MIX (3;B) | TON | 15,067 | $49.00 | $738,283.00 | $53.50 | $806,084.50 | $62.83 | $946,659.61 | $67.49 | $1,016,871.83 |
2360.509 | TYPE SP 9.5 BIT MIXTURE FOR PATCHING | TON | 300 | $80.00 | $24,000.00 | $299.00 | $89,700.00 | $196.82 | $59,046.00 | $216.64 | $64,992.00 |
2563.601 | TRAFFIC CONTROL | LS | 1 | $5,500.00 | $5,500.00 | $39,792.00 | $39,792.00 | $5,114.32 | $5,114.32 | $29,090.90 | $29,090.90 |
2582.503 | 4" SOLID LINE MULTI COMP | L F | 61,850 | $0.25 | $15,462.50 | $0.30 | $18,555.00 | $0.28 | $17,318.00 | $0.34 | $21,029.00 |
2582.503 | 24" SOLID LINE MULTI COMP | L F | 82 | $15.00 | $1,230.00 | $11.00 | $902.00 | $10.03 | $822.46 | $12.18 | $998.76 |
2582.503 | 4" BROKEN LINE MULTI COMP | L F | 5,120 | $0.25 | $1,280.00 | $0.30 | $1,536.00 | $0.28 | $1,433.60 | $0.34 | $1,740.80 |
2582.518 | PAVT MSSG MULTI COMP | S F | 196 | $11.00 | $2,156.00 | $10.50 | $2,058.00 | $9.53 | $1,867.88 | $11.57 | $2,267.72 |
| Totals for project 85-21 | | $882,677.60 | | $1,044,621.45 | | $1,158,564.07 | | $1,241,558.31 |
|
Contract Total: | $882,677.60 | $1,044,621.45 | $1,158,564.07 | $1,241,558.31 |